Business registration, licences & compliance — online across India +91 92205 65553info@lawgicalguru.in
Lawgical Guru
Business setup
Licences & NOCs

Food, Drug & Health

FSSAI Food Licence & RegistrationDrug Licence (Retail and Wholesale)Cosmetic LicenceMedical Device Registration (CDSCO)AYUSH Manufacturing LicenceClinic Registration (Clinical Establishments)Spices Board Registration (CRES) for ExportersAPEDA Registration (RCMC) for Agri and Food ExportersLiquor Licence for Bar & Restaurant

Factory & Labour

Factory Licence RegistrationContract Labour LicenceBOCW RegistrationESIC RegistrationPF Registration (EPFO)Labour Welfare Fund (LWF) RegistrationLabour Identification Number (LIN)Professional Tax RegistrationShop and Establishment Registration

Municipal & Building

Trade LicenceHealth Trade LicenceEating House LicenceMeat Shop & Meat Trading LicenceSignage (Advertisement Board) LicenceHawker / Street Vendor LicenceFire NOC (Fire Safety Certificate)Building Plan Approval

Trade, Finance & Specialised

Import Export Code (IEC) RegistrationICEGATE RegistrationRCMC RegistrationLEI RegistrationDigital Signature Certificate (DSC)Barcode (GS1) RegistrationLegal Metrology (LMPC) RegistrationWeights & Measures (Legal Metrology) LicenceFertilizer LicenceMining Lease & Mining NOCPESO LicencePSARA Licence (Private Security Agency)RERA Project RegistrationRERA Agent RegistrationRNI Registration (PRGI Periodical Registration)NBFC RegistrationIRDAI Licence (Insurance Broker & Corporate Agent)

Pollution Consents

Pollution NOC (Consent to Establish & Operate)Groundwater NOC (CGWA / State Authority)

Waste Authorisations & EPR

Bio-Medical Waste Authorisation (BMW Rules)Hazardous Waste Authorisation (HOWM Rules)E-Waste EPR Registration (CPCB)Plastic Waste EPR Registration (PIBO / PWP)

Product & Quality Certification

ISI Mark CertificationBIS CRS RegistrationBIS Hallmark RegistrationISO CertificationCE CertificationHalal CertificationUS FDA Registration for Indian ExportersHACCP Certification All licences
Tax & compliance
Trademark & legal
Industries
Guides About us Contact Free consultation Call +91 92205 65553

Setting Up a Manufacturing Unit in Noida: Approvals in Order

The order in which a manufacturer should secure land, plan sanction, pollution consent, fire, factory licence and labour registrations in Noida, with Nivesh Mitra tips.

By Satyam Gupta, Company Secretary (CS) & Advocate · Published 16 October 2026

To set up a manufacturing unit in Noida, you first secure legally usable industrial land from the right authority, then get the building plan sanctioned, then obtain pollution consent, fire safety, groundwater and power approvals, and only then apply for the factory licence and start production. Many of these applications run through the Uttar Pradesh single-window portal, Nivesh Mitra, but the order matters because later approvals quote the earlier ones.

This guide is a sequencing checklist for first-time and growing manufacturers. It does not quote plot rates, fees or allotment conditions, because those change from scheme to scheme and must be read from the authority's current brochure.

Which authority controls your land?

"Noida" is used loosely. The industrial area you choose decides who allots the land, who approves the building plan and who collects the dues. In Gautam Buddh Nagar district the main bodies are:

  • Noida Authority (New Okhla Industrial Development Authority), which controls the older, planned sectors of Noida.
  • GNIDA (Greater Noida Industrial Development Authority), which controls Greater Noida's industrial sectors and has run online e-auctions for industrial plots, with brochures published on its website and on Nivesh Mitra.
  • YEIDA (Yamuna Expressway Industrial Development Authority), which controls land along the Yamuna Expressway.
  • UPSIDA (Uttar Pradesh State Industrial Development Authority), which develops industrial areas elsewhere in the state.
  • Private landowners or existing industrial units, if you buy or lease a built shed. In that case your rights flow from the lease or sale deed and the authority's transfer permission.

Before you pay anything, confirm in writing which authority owns the land, what land use is recorded, and whether the plot is allotted to the seller on a lease that permits sub-lease, transfer or your type of manufacturing. This one check saves more money than any other step in the guide.

The approvals in order

The table gives the sequence most manufacturers follow. Some steps run in parallel, and the exact forms and portals depend on the authority and industry category.

Stage What you obtain Who issues it Why it comes here
1 Business entity, PAN, bank account MCA / Registrar or LLP/partnership registry Land, loans and approvals need a legal entity
2 Land or shed: allotment, lease or purchase Noida Authority, GNIDA, YEIDA, UPSIDA or private owner Every later approval needs the site address and title
3 Udyam registration, GST registration MoMSME portal, GST portal Needed for subsidies, bank loans and invoicing
4 Building plan sanction Authority that owns the land Construction should not start without it
5 Consent to Establish (CTE) Uttar Pradesh Pollution Control Board Needed before you install machinery for polluting categories
6 Groundwater permission, where you will draw water State groundwater authority Pollution consent often asks for the water source
7 Fire safety clearance, where applicable UP Fire and Emergency Services Depends on building height and use
8 Electricity connection Local distribution licensee Load is needed for factory licence slab
9 Factory licence and plan approval State labour or factory department under the OSH Code Required before you start manufacturing
10 Consent to Operate (CTO) UPPCB Required before commercial production
11 PF, ESIC, professional tax and other labour registrations EPFO, ESIC, state Triggered when you hire
12 Product licences (BIS, legal metrology, FSSAI etc.) Relevant regulator Depend on what you make

Step 1: choose the entity and the registrations that depend on it

Choose the entity before you apply for land, since allotment letters, sanction plans and licences are issued in that name and changing it later means amendments and sometimes fresh consent. Most manufacturers choose a private limited company or an LLP. A proprietorship works for very small units but limits fund-raising and can complicate licence transfers.

Then register for GST at the site address and obtain Udyam registration. Do both early. Banks, subsidy schemes and many authority forms ask for them, and a mismatch in name or address across these records is a classic cause of queries later.

Step 2: secure the land or shed

There are two common routes.

Allotment from an authority. Authorities publish schemes with a brochure that sets eligibility, plot sizes, the manner of allotment (for example online e-auction), payment schedule, construction timelines and conditions. Read the brochure on the authority's own website. Do not rely on a broker's summary of price or conditions, since these vary by scheme and by year. Check the following in the brochure and the allotment letter:

  • Permitted activities and any restricted or prohibited industries.
  • Time limits to construct and commence production, and consequences for delay.
  • Rules on sub-lease, transfer, mortgage and change of use.
  • Dues payable on transfer or change of name.

Buying or leasing an existing unit. Ask for the chain of title, the authority's no-dues certificate and the sanctioned plan. Check that the structure matches the sanctioned plan, because deviations surface when you apply for consent or a factory licence. Also confirm that the previous occupier's licences have been surrendered or can be amended, since an occupied building may still carry old consents that do not match your products.

If you are comparing sites, also read our guide on building plan approval to understand how the authority checks coverage, setbacks and use.

Step 3: building plan sanction

The authority that owns the land sanctions the plan. Typically the submission includes the layout, structural and fire drawings by registered professionals, the allotment or lease documents, and the process details if the authority asks. Do not begin construction on the strength of an application alone; keep the sanction letter and any later revised plans in a single file.

Under the OSH Code, a factory also needs approval of its plans for the factory building and layout from the labour or factory authority. Our factory licence research notes that the Code provides for a deemed permission if the authority does not respond within 30 days, but that is only useful if you can prove the date of submission, so keep the acknowledgement. Rules for this stage are in the Uttar Pradesh OSH rules notified in August 2026, so check the current UP forms rather than older Factories Act practice.

Industrial units that may pollute need Consent to Establish (CTE) before construction or installation of plant and Consent to Operate (CTO) before production begins, from the state pollution control board. The category (Red, Orange, Green, White or Blue) follows the CPCB's 2025 classification, and White category industries were exempted from consent through 2024 notifications of the environment ministry, so do not assume consent applies to you without checking the category for your product. Our pollution NOC page explains category, validity and fees.

Practical points specific to a planned industrial area:

  • A clear process flow chart decides the category dispute faster than any other document.
  • Keep the capital investment figure the same across your consent application, Udyam record, bank appraisal and subsidy claims.
  • CTE is not permission to operate. Commercial production without CTO is treated as operating without consent.

Step 5: water, fire and power

Groundwater

If any water will be drawn from a borewell, check whether a groundwater permission is required for your activity and location. Pollution consent applications commonly ask for the source of water, and the water balance must add up. Start the application in parallel with consent. See groundwater NOC.

Fire

Fire safety rules in Uttar Pradesh sit under the UP Fire and Emergency Services Act, 2022 as amended in 2026. Whether you need a certificate depends on building height and use, and the department must be satisfied about exits, hydrants, pumps and alarm systems. Align the fire consultant with the architect before the plan is sanctioned, because moving a staircase or pump room later is expensive. See fire NOC.

Electricity

Apply for the load you actually need. The sanctioned load and the installed horsepower feed into your factory licence slab, and mismatches between the electricity bill and the factory licence application trigger queries.

Step 6: factory licence

Once the building and machinery are ready, apply for the factory licence on the state portal. The Uttar Pradesh rules notified in August 2026 set out the forms, the fee matrix by power and headcount, and the validity, which our research records as one year initially with renewal for longer periods. Verify the live fee computed by the portal rather than relying on any figure in a blog post.

Keep these ready:

  • Sanctioned plan and plan approval for the factory.
  • Occupier details and a resolution naming the occupier if the unit is a company or LLP.
  • Machinery list with horsepower, and the maximum number of workers you expect on any day, including contract workers.
  • Pollution consent and fire clearance, where relevant.

Step 7: hiring registrations

Register under PF and ESIC as your headcount crosses the thresholds, and obtain a contract labour licence if you will use contractors. Add professional tax and labour welfare fund as applicable in UP. Our labour codes compliance calendar for small manufacturers lists the recurring dates once you are live.

Using Nivesh Mitra

Nivesh Mitra is the Uttar Pradesh single-window portal where many state-level approvals, including pollution consent, labour registrations and other clearances, can be filed and tracked in one place, and where authority schemes and brochures are sometimes also published. It helps because status, queries and payments sit together. Its limits are practical: some approvals still depend on separate local offices, uploads need consistent names and addresses across documents, and an unanswered query can reject an application. Assign one person to watch notifications daily.

Common sequencing mistakes

  • Starting construction before sanction. Regularising unsanctioned construction is slower than waiting.
  • Buying machinery before CTE. Installed but unapproved capacity is treated as a violation.
  • Using different addresses. GST, Udyam, the allotment letter and the licence must all carry the same address and name.
  • Ignoring the land use clause. A plot allotted for one activity cannot automatically be used for another.
  • Not budgeting for time. Authorities and boards do not commit to timelines. Build slack into your launch plan and your lender's drawdown schedule.
  • Starting production on a partial set. CTO, factory licence and fire clearance should be in place before commercial production.

A one-page launch checklist

  1. Confirm authority, land use and permitted activity in writing.
  2. Incorporate the entity; open the bank account; register GST and Udyam.
  3. Obtain allotment or lease; record the possession date.
  4. Get plan sanction from the land authority and factory plan approval.
  5. File CTE and groundwater application with consistent investment and water data.
  6. Complete construction to the sanctioned plan; install fire systems.
  7. Obtain power connection and apply for the factory licence.
  8. Obtain CTO and fire clearance; then start commercial production.
  9. Register PF, ESIC and other labour registrations as you hire.
  10. Set up the recurring compliance calendar.

If you want a second pair of eyes on the sequence for a specific plot or industry, Lawgical Guru's Noida office can review your documents before you file.

Frequently asked questions

Which authority allots industrial plots in Noida?

It depends on the area. Noida Authority controls the older Noida sectors, GNIDA controls Greater Noida's industrial sectors, YEIDA controls Yamuna Expressway land, and UPSIDA develops industrial areas elsewhere in the state. Read the current scheme brochure of the relevant authority before paying anything.

What is Nivesh Mitra?

Nivesh Mitra is the Uttar Pradesh single-window portal where many state-level business approvals can be applied for and tracked. Authority scheme brochures, including GNIDA's, have also been published there. Some approvals still depend on separate offices, so check each application's status individually.

Do I need pollution consent before building a factory?

If your product falls in a category that requires it, you need Consent to Establish before construction or machinery installation, and Consent to Operate before production. White category industries were exempted by 2024 notifications, so confirm your category under the CPCB 2025 classification first.

Can I start production once the factory licence is issued?

Not automatically. You also need Consent to Operate where consent applies, fire clearance where applicable, and registrations such as PF and ESIC once you employ people. Starting production on a partial set of approvals can be treated as operating without consent.

Should I buy a ready shed or allotted plot?

A ready shed saves time but you inherit its title chain, sanctioned plan and any old consents. An allotted plot gives a clean start but comes with construction and commencement timelines in the brochure. Check transfer permission and no-dues certificates in either case.

How long will all the approvals take?

No single timeline applies. Timing depends on the authority, your industry category, the completeness of documents and inspections. Plan with slack and avoid committing to a launch date or loan drawdown on the assumption that approvals will arrive within a fixed period.

Official sources

  1. Nivesh Mitra - Uttar Pradesh single window
  2. Greater Noida Industrial Development Authority
  3. The Week - UP govt begins e-auction of industrial plots in Greater Noida (30 May 2025)
  4. Uttar Pradesh Fire and Emergency Services Act, 2022 (India Code)
  5. PIB - Four Labour Codes come into effect (21 Nov 2025)

Reviewed by Satyam Gupta, Company Secretary (CS) & Advocate

8+ years of industry experience. Last reviewed 16 October 2026. Always confirm current rules and fees on the official portal before acting.

Not sure which licence or registration applies to you?

Tell us your activity and location. We'll map the approvals you need and the order to get them in.